ADU Permit & Impact Fees in California (2026)
Permit and fee costs for an ADU in California usually run from about $5,300 for a small conversion to $37,400 or more for a large detached unit in an expensive city. Size is the biggest lever: two state rules make units under 500 and 750 sq ft much cheaper to permit.
What you pay for
| Fee | Who charges it | Typical amount |
|---|---|---|
| Plan check | City or county building department | Often 40-80% of the building permit fee |
| Building permit | City or county | Based on project value; often a few thousand dollars |
| Impact fees | City, county, special districts | $0 under 750 sq ft; proportional above |
| School fees | Local school district | About $5.17 per sq ft, only over 500 sq ft |
| Utility connection | Water, sewer and power providers | Varies widely; a new meter can cost thousands |
The 500 and 750 sq ft lines
Under state law, cities and special districts cannot charge impact fees on an ADU under 750 sq ft. School districts can charge school fees only on ADUs over 500 sq ft. For a 749 sq ft ADU you avoid impact fees but pay school fees; at 500 sq ft or less you avoid both.
Using our model, here is how fees change with size for a detached ADU at the state average:
| ADU size | Permits | School fees | Impact fees | Total fees |
|---|---|---|---|---|
| 400 sq ft | $5,900 | $0 | $0 | $5,900 |
| 500 sq ft | $6,500 | $0 | $0 | $6,500 |
| 600 sq ft | $7,100 | $3,100 | $0 | $10,200 |
| 749 sq ft | $8,000 | $3,900 | $0 | $11,900 |
| 750 sq ft | $8,000 | $3,900 | $6,800 | $18,600 |
| 1000 sq ft | $9,500 | $5,200 | $9,000 | $23,700 |
| 1200 sq ft | $10,700 | $6,200 | $10,800 | $27,700 |
Utility connection fees
Water and sewer agencies cannot charge a connection fee or capacity charge for an ADU created inside an existing house or accessory structure (a conversion or JADU) unless it is built with a new home. For new detached units, they may charge fees that are proportional to the ADU's impact. A separate electric meter is optional in most cases, but some owners pay for one so the tenant can be billed directly.
How to keep fees down
- Keep the ADU under 750 sq ft, or at 500 sq ft or less for the lowest fees.
- Use your city's pre-approved plans if it has them. Plan check is often faster and sometimes cheaper.
- Ask the building department for a fee estimate before you finish design. Most will give one.
- Submit a complete application. Resubmittals add time, and some cities charge extra for additional plan reviews.